EEPCO to Inaugurate Adama I
The Ethiopian Electric Power Corporation is to inaugurate Adama I wind Farm on the 1st of December. The project completed at a total cost of 117 million US dollars was constructed with an installed generation capacity of 51 Mega Watts.The Adama Wind farm has a total of 34 towers with the ability to generate 1.5 MW each.
Eight five percent of the 117 million US dollar budget was covered by a loan arranged by the Export-Import bank of China. The Ethiopian government covered the remaining fifteen percent in financing.
The mechanical work for the wind farm was handled by Hydro China and the civil work was taken care of by CGOC.