The Ethiopian Electric Utility (EEU) has announced the completion of 2,472 kilometers of electricity line reconstruction, upgrading and expansion projects during the first four months of the current Ethiopian fiscal year.
According to a statement issued by EEU, the projects were financed entirely through the institution’s internal resources, reflecting ongoing efforts to strengthen electricity distribution infrastructure and expand access to power across the country.
Of the total work completed, 831 kilometers involved the rehabilitation and upgrading of existing electricity networks, comprising 749 kilometers of medium voltage lines and 82 kilometers of low voltage lines.
As part of the rehabilitation efforts, the utility replaced 481 overloaded transformers with higher capacity units to reduce service interruptions and improve the reliability of electricity supply. An additional 411 transformers were installed in various locations to strengthen distribution capacity.
The utility also reported progress in expanding electricity coverage, constructing approximately 1,641 kilometers of new distribution lines. These included 978 kilometers of medium voltage lines and 662 kilometers of low-voltage lines.
Furthermore, 1,744 transformers were installed under the network expansion program to support electricity distribution in newly served areas.
The utility stated that the completed projects form part of its broader efforts to modernize the country's electricity distribution network, address infrastructure limitations and improve service reliability.